The full list of rail projects: under construction and the new generation

The list of the large and small rail projects constructed and is going to be auctioned off gave the …
publicity the ERGOSE.
I. AXIS ATHENS – THESSALONIKI
IN PROGRESS
– Completion of the new double ηλεκτροκινούμενης
high speed railway line in the section
Tithorea-Lianokladi-Domokos, with a length of 106 km. Completion : June 2018
– Construction of Lower Ford street St. Friday
in New york. Menemeni Thessaloniki Completion : February 2018
TO ΔΗΜΟΠΡΑΤΗΣΗ THE PERIOD 2017
– Technical monitoring of large bridge section Lianokladi – Domokos
– Construction of railway policy stance in law. Panteleimon, Pieria
– Construction of new rail/european bridge to the French river
II. AXIS ATHENS – PATRAS
IN PROGRESS
– Construction of a new double σηματοδοτούμενης line
Kiato – Diakopto – Rododafni, approximately 71 km. Completion : December 2017
– Construction of infrastructure works in the section Rododafni
(km. 91,5) – Psathopyrgos (km. 113) of the new railway
line Athens-Patras, Completion : December 2017
IN PHASE AWARD
– Construction of infrastructure works in the department Involves the
(km. 113) – Patras (area Μποζαΐτικα) (km. 123,5)
TO ΔΗΜΟΠΡΑΤΗΣΗ THE PERIOD 2017
– Electrification of railway/kis line Kiato – Rhododendron
– Construction of superstructure, signalling and electrification of the new railway policy
line Rododafni – Psathopyrgos
III. WORKS WIDER AREA OF ATHENS
IN PROGRESS
– Construction B Operational Phase
Of Thriassio Pedio Complex Completion : February 2017
– Completion of two ηλεκτροκινούμενης line
Piraeus – P.P. Athens Completion : June 2017
TO ΔΗΜΟΠΡΑΤΗΣΗ THE PERIOD 2017
– Remaining work within In.P. Athens and connect with Metro (phase B)
– Construction of a quad rail corridor in the section and Exit through.P. Athens (P.P.A.) – Three Bridges, with lowering in the area of Sepolia
IV. AXIS THESSALONIKI – ΕΙΔΟΜΕΝΗ
IN PROGRESS
– Construction of a variant of the railway line
in the section Polykastro-Eidomeni, with a length of 21 km. Completion : December 2017
V. WORKS SIGNALLING AND TELECOMMUNICATIONS
IN PROGRESS
– Completion of signalling and telecommanding ETCS – level 1
in the sections of the SKA-Thessaloniki-Promachon Completion : December 2017
– Supply of system hacking GSM-R on the axis
PATHE/P (other than section Tithorea-Domokos, Thessaloniki-Ειδομένης
and Kiato-Patra) Completion : December 2016
TO ΔΗΜΟΠΡΑΤΗΣΗ THE PERIOD 2017-2018
– Installation of ETCS signalling on the line Thessaloniki-Idomeni
– Installation of system hacking GSM-R in section Tithorea-Domokos, Thessaloniki-Eidomeni and SKA-Patras
VI. REGIONAL RAILWAY NETWORK.
TO ΔΗΜΟΠΡΑΤΗΣΗ THE PERIOD 2017
– Variation of rail/kis line in section P.P. Quarry-marble, and installation
signalling and electrification on the line Larissa-Volos
– Normalization and electrification of railway/kis line Isthmus-Loutraki
– Installation of signalling and electrification on the line
Παλαιοφάρσαλος-Kalambaka
VII. SUGGESTIONS OF WORKS FOR INCLUSION IN THE PACKAGE PAPAIOANNOU
The Ministry of Infrastructure and Transport, in cooperation with ERGOSE, has submitted 4 proposals for combined transport which have been deposited in the Investment Portal of the Commission to find funding for the Plan Juncker.
The 4 proposals as tabled are the following:
1) Western Axis Of The Peloponnese
• The project includes the design, construction, financing, management, maintenance and exploitation of railway lines, ports and road segments in Western Peloponnese. The line linking Patra – Pyrgos– Kalamata with a connection to Ancient Olympia and Katakolon. The train will connect four ports cruise (Patras, Kyllini, Katakolo, Kalamata). With center Olympia can be a pole of attraction for investment on the basis of tourism.
2) Railway Line Athens-Lavrio
• The project is an extension of the suburban as the port of Lavrion. The Port may be dedicated to passenger ships from North and Central Aegean sea. The aim is to host and cruise ships can reach the port of Lavrion rather than Piraeus. The project may be part of a wider project that involves the Attiki Odos motorway, the Port and the Suburban.
3) Upgrade Railway Line Alexandroupoli-Ormenio
• The project involves the installation of electrification and signalling on the section Alexandroupoli-Ormenio-Bulgarian Border, with a length of 175 km, with a parallel upgrade of the Port of Alexandroupolis in the field of freight transport.
4) Railway Egnatia
• The project concerns the construction, financing, management, operation, maintenance, and operation of the Rail Corridor from Alexandroupolis to the Port of Igoumenitsa.
Source