The Hellenic Electricity Distribution Network Operator (DEDDHE) has conducted a series of studies focused on Fyli and Aspropyrgos, aiming to optimize energy flow management and ensure efficient operation of the local electricity grid. In addition, several underground power line projects have already been completed in the region.
In the area of Fyli, four undergrounding projects for the existing Medium Voltage (MV) network have been completed, resulting in 14.7 km of underground cables and the removal of 4.39 km of overhead lines. Two additional projects are currently underway, with 13.3 km of MV underground cables already installed. To complete these works, an additional 14.34 km of underground network will be installed, while another 6.48 km of overhead MV lines will be removed.
In the Nea Zoi settlement of Aspropyrgos, a project to underground part of the existing MV network has been completed, including 5.08 km of underground cabling and the removal of 2 km of overhead lines.
In Melissia (Aspropyrgos municipality), a new underground interconnection line was built to improve network management and speed up fault restoration. The project included 290 meters of underground MV cable and 321 meters of overhead MV line.