New Spatial Planning Framework Opens for Consultation: Where Solar and Wind Farms Are Banned

—

in

Public consultation on Greece’s new spatial planning framework begins today. The framework introduces revised rules for siting new renewable energy installations—including solar and wind farms—as well as energy storage facilities across the country.

Solar Power Restrictions

Under the draft plan, photovoltaic (PV) power stations are prohibited in the following areas:

  • All NATURA 2000 protected sites;
  • Forests and forested land;
  • Ramsar wetlands and small island wetlands;
  • National parks, officially designated natural monuments, and aesthetically protected forests;
  • Landscapes of Outstanding Natural Beauty;
  • UNESCO World Heritage Sites, other monuments of major significance, and Zone A archaeological protection zones;
  • Areas containing protected or abandoned terraced farming systems;
  • Off-road areas, as defined by decisions of the Ministry of Environment and Energy (YPEM);
  • Bathing beaches.

In addition, new siting criteria apply. For instance, the maximum permitted ground coverage by new PV installations is capped at 1.5% per regional unit. Minimum setback distances from residential and other human settlements are also mandated. A specialized environmental impact study will be required for any PV installation proposed near UNESCO sites or archaeological areas.

Wind Farm Restrictions

Wind farms are banned in several key locations, including:

  • Attica region and the metropolitan area of Thessaloniki;
  • Areas above 1,200 meters in elevation;
  • Ramsar wetlands and small island wetlands;
  • Landscape Areas of Outstanding Natural Beauty—and within the core zones of national parks;
  • Zones of absolute and general nature protection under Law 1650/1986;
  • Islands smaller than 300 square kilometers—unless serving a clear public interest need (e.g., desalination plants);
  • Areas with high tourism development, as defined in the new Special Spatial Framework for Tourism;
  • Out-of-plan zones earmarked for tourism and leisure development;
  • Active surface mining and quarrying zones;
  • Off-road areas, as defined by YPEM decisions;
  • Bathing beaches;
  • Special Protection Areas (SPAs)—NATURA 2000 sites designated for bird conservation.

Within SPAs, wind farms may only be approved exceptionally—and only if two strict conditions are met simultaneously. These include, among other requirements, that the project must not adversely affect protected bird species or their habitats, and that no viable alternative location exists outside protected zones.