More than a decade after it was originally due, Greece’s new Special Spatial Planning Framework for Renewable Energy Sources (RES) was officially presented on 20 May 2026. The long-delayed framework has drawn criticism from environmental organisations across the country.
Stricter, Location-Specific Rules
The framework — now open for public consultation — introduces targeted restrictions on where RES projects can be sited. For example, wind farms are now prohibited at elevations above 1,200 metres. According to Deputy Minister of Energy Nikos Tsafos, the underlying principle is a shift from permissiveness to selectivity: “If you could previously develop RES projects in ten locations, now you can do so in only four or five.” He stressed that the Ministry of Environment and Energy (YPEM) has responded directly to public concerns by adopting more precise and stringent spatial rules.
Photovoltaics: A Regional Cap Instead of a National One
A key consideration for solar projects was how to set a fair cap on land use. Rather than applying a uniform national percentage, the ministry opted for a regional approach. “We saw huge disparities between regions — some with very high potential, others with very low. A flat nationwide figure would have been either excessively high for some or far too restrictive for others,” Tsafos explained. “Given this heterogeneity, we settled on a limit of 1.5% of the total area of each regional unit.”
Too Little, Too Late?
Despite its intentions, the new framework’s real-world impact remains questionable. Crucially, its restrictions do not apply retroactively: they exclude all projects that have already received Environmental Terms Approval (AEPO) decisions or have completed their permitting dossiers. In practice, this means over 100 GW of RES capacity — currently in the pipeline — falls outside the new rules.
This volume alone far exceeds Greece’s official targets: the National Energy and Climate Plan sets goals of 13.5 GW of solar capacity by 2030 (rising to 35 GW by 2050), and 8.9 GW of wind power by 2030 (13 GW by 2050). With around 18 GW already installed and another ~100 GW in various stages of approval, the theoretical pipeline could meet national RES needs well into the second half of the century.
In reality, however, much of this pipeline will never be built. Market demand, financing readiness, commercial conditions, and other practical constraints mean many projects will stall or be abandoned. That said, there may still be room for new developments under the updated spatial framework — especially to fill any gaps left by unrealised projects. Still, such projects would represent only a fraction of future RES investment in Greece.
Ultimately, while the new spatial plan aims to bring order to what had become a largely unregulated expansion of RES infrastructure, it arrives so late in the development cycle that its ability to meaningfully reshape the landscape — or alleviate local opposition — is severely limited.