Greece’s carbon capture, transport, and underground storage (CCS) infrastructure is entering an implementation phase, with two flagship projects moving forward: DESFA’s initiative at Revythousa and EnEarth’s project at Prinos. Both have secured significant funding from national and European sources, targeting a final investment decision and the start of drilling operations by 2027.
The APOLLOCO₂ Project
The integrated APOLLOCO₂ project has been designated a Project of Common Interest (PCI) by the European Commission. It targets industrial emitters that lack the technological means to reduce CO₂ emissions directly—leaving them exposed to rising carbon pricing costs. The solution involves capturing CO₂ at source facilities, transporting it via pipeline to DESFA’s Revythousa terminal, liquefying it there, loading it onto ships, and delivering it to Prinos for permanent underground storage at depths of 2,500–3,600 meters in the depleted Prinos oil field.
Revythousa: Leveraging Existing LNG Infrastructure
Last week, DESFA and the European Commission signed a €169.3 million grant agreement under the Innovation Fund to build a CO₂ liquefaction, temporary storage, and export facility at Revythousa. The site already handles liquefied natural gas (LNG), which arrives at ultra-low temperatures and requires energy-intensive regasification before entering transmission pipelines. Crucially, the existing cryogenic infrastructure at Revythousa will be repurposed to cool and liquefy CO₂—significantly cutting energy demand and operational costs.
DESFA also plans to develop dedicated CO₂ transport pipelines connecting regional industrial facilities to Revythousa.
Prinos: Preparing for Storage Operations
On the receiving end, technical and financial maturity of the underground storage site at Prinos is progressing. Next steps include regulatory approval from Greece’s Energy Regulatory Authority and completion of two market test phases—non-binding and binding—to inform the final investment decision, expected in the first half of 2027.
A new offshore platform, currently undergoing commissioning in Perama, will soon be deployed to Prinos. Early next year, the first of six planned CO₂ injection wells will begin drilling—the first step toward operational storage.
Funding and Scale
The Prinos storage facility and associated infrastructure have secured €120 million from the Connecting Europe Facility and €150 million from Greece’s National and Development Public Investment Programme—including €75 million drawn from the Recovery and Resilience Fund. In total, €270 million has been committed toward the project’s €1 billion total investment.
Both the Revythousa and Prinos components are designed to operate independently—meaning they can accept CO₂ from sources beyond the initial project partners. Preliminary market interest from Greek industry already exceeds the storage capacity planned across the project’s two phases, which together aim to store up to one million tonnes of CO₂ annually.