Anxiety and fear have gripped residents of Kypseli in recent days following the appearance of cracks in homes—linked to ongoing construction works for Athens Metro Line 4. A high-level meeting addressing this serious issue took place this Thursday morning (16 July 2026) at the Kotzia Municipal Building, bringing together Athens Mayor Haris Doukas and a delegation from the management and technical staff of Elliniko Metro.
Three Key Demands Raised by the Mayor
Following the meeting, Mayor Doukas reaffirmed the municipality’s unwavering support for affected residents and outlined three core demands presented to the contractor. He confirmed that approximately 200 residences—and thus some 200 families—have sustained damage.
First, the city is calling for written guarantees on the structural integrity of affected buildings, backed by certification from an independent, public authority qualified to verify their static safety.
Second, it has demanded the immediate initiation of legally mandated compensation and restoration procedures for all damaged properties.
Third, while affirming strong municipal support for completing Metro Line 4, Doukas stressed that all future work must strictly adhere to existing safety regulations and engineering standards.
Tunneling Paused Amid Challenging Geology
Excavation work in Kypseli is currently suspended. Mayor Doukas acknowledged the area’s known geological sensitivity—including underground streams—which had prompted the installation of around 3,000 monitoring sensors along and around the tunnel route. He noted that the tunnel boring machine (TBM) has already halted twice due to anomalies detected by these systems, and is now fully paused pending resolution.
Expert Review Underway
To resolve the impasse and ensure safe resumption of works, Elliniko Metro has commissioned a team of specialists—including professors and experts from Greece and abroad. Among them are researchers from the National Technical University of Athens (NTUA) and an international expert. Their task is to propose a technically sound, safety-first plan for restarting tunneling in the area.
Doukas added that the timeline for delivering this expert assessment is urgent—the responsible team has informed the municipality that their findings will be ready shortly.