Driven by robust first-quarter financial results, Greece’s Independent Power Transmission Operator (ADMIE) is set to move forward with a €1 billion capital increase planned for completion by June.
Strong Financial Performance
The company reported an 18.6% year-on-year rise in annual revenues to €133 million, EBITDA up 18.4% to €97.4 million, and comparable net profits up 21.9% to €47.7 million. Key contributors included transmission system usage fees and balancing market revenues, which together reached €130 million—up from €110 million last year—providing a solid foundation ahead of the capital increase.
Investment Priorities and Ongoing Projects
Capital expenditures dropped to €46.8 million in the first quarter, down from €84.7 million a year earlier—largely reflecting the completion of the major Crete interconnection at the end of last year.
Among priority infrastructure projects, the fourth Cyclades interconnection—linking Santorini, Folegandros, Milos, and Serifos—is now on track for completion. The 400 kV transmission line between the Korinthos and Koumoundourou substations is scheduled for completion by 2026, while upgrades to the Koumoundourou substation are already underway.
International Interconnections
For the new interconnection with Italy, the Environmental Impact Assessment is expected to be issued in August; meanwhile, bids for seabed survey studies are under evaluation.
By year-end, ADMIE also aims to finalize commercial viability studies for its ambitious interconnection project with Saudi Arabia—a proposal that has re-emerged amid the European Union’s broader initiative to support €25 billion in Mediterranean energy infrastructure investments by 2035. Earlier this week, EU officials confirmed that ADMIE’s Saudi link is among the projects currently under consideration for potential funding support.